New Orleans — Opening Set
Rail Transit Online, May 2003
Oct. 11 has been set as the
opening date of the 3.1-mi. (5 km) Canal Street trolley line between the
Mississippi River and the Cemeteries. The one-mile (1.6 km) spur along
North Carrollton Avenue is tentatively set for completion by the end of
December. However, with the $161-million project now 65 percent finished,
the scheduled openings depend on a lack of construction delays caused by
inclement weather or other problems. Track installation is still underway
at several locations along Canal Street and 11 of the 24 new replica
heritage streetcars needed for the line have been assembled by RTA shop
forces at the Carrollton car barn. The trolleys will bear a resemblance to
the original Perley Thomas streetcars still running on the St. Charles line
but are equipped with air conditioning, modern propulsion gear, wheelchair
lifts and are painted apple red instead of green. |
|